Playground Upgrades in full swing!
14 August 2026
Work is continuing across the district as part of our playground upgrade programme, with several sites already underway or nearing completion.
- Norsewood – We’ll be back at the playground shortly to complete the remaining work around the Roktapus.
- Ormondville – The upgrades are progressing well and are almost finished! The new equipment is in place, with the remaining finishing work to be completed shortly.
- Pahiatua – Work is scheduled to get underway Monday 17 August, weather permitting. This will include timber edging around the horizontal wooden rocker and a top-up of the safety bark.
We’ll keep you updated as work progresses at the remaining playgrounds around the district.
Thanks for your patience while these improvements are completed – we’re looking forward to seeing more of our upgraded playgrounds ready for the community to enjoy!
See our original news item for the full programme and what’s planned at each playground: